#1
|
Functioning Normally, Ready for test
rack. Main DDS sample output added for phase testing.
|
#2
|
Functioning Normally, Ready for test
rack. Main DDS
sample output added for phase testing. |
#3
|
Completed Construction.
Debugging in LO Lab, Due September 1st
|
#4
|
Under
Construction in LO lab, Due
September 1st, delayed due to parts delivery (Norden) |
#5
|
Under
Construction in LO lab, Due
September 1st, delayed due to parts delivery (Norden) |
#6
|
Under
Construction in LO lab, Due
September 1st, delayed due to parts delivery (Norden) |
#7
|
Construction
planned for Ready Service Spare as parts become available, possibly use
breadboard components. No Due Date Planned
|
#8
|
Production version depends
on Delivery of AGC subassy from Miteq. Planned for Jan 1,
2005 |
#8
|
Production version depends
on Delivery of AGC subassy from Miteq. Planned for Jan 1,
2005 |
#10
|
Production version depends
on Delivery of AGC subassy from Miteq. Planned for Jan 1,
2005 |
#11
|
Production version depends
on Delivery of AGC subassy from Miteq. Planned for Jan 1,
2005 |