Sep 13, 2004

L301 Status

Done
Pending
Late

#1
Installed in test rack.  Functioning Normally
#2
Installed in test rack.  Functioning Normally
#3
Under Construction in LO lab, delayed due to parts delivery (Norden) to Oct 22 nd
#4
Under Construction in LO lab, delayed due to parts delivery (Norden) to Oct 22 nd
#5
Construction planned for Ready Service Spare as parts become available, possibly use breadboard components. No Due Date Planned
#6
Production  version  depends on  Delivery of AGC subassy from Miteq.  Planned for Jan 1, 2005
#7
Production  version  depends on  Delivery of AGC subassy from Miteq.  Planned for Jan 1, 2005


L302 Status


#1
Functioning Normally, Installed in test rack.  Main DDS sample output added for phase testing.
#2
Functioning Normally, Installed in test rack.  Main DDS sample output added for phase testing.
#3
Completed Construction. Debugging in LO Lab, Due September 1st
#4
Under Construction in LO lab, Due September 1st, delayed due to parts delivery (Norden), and machine shop load
#5
Under Construction in LO lab, Due September 1st, delayed due to parts delivery (Norden), and machine shop load
#6
Under Construction in LO lab, Due September 1st, delayed due to parts delivery (Norden), and machine shop load
#7
Construction planned for Ready Service Spare as parts become available, possibly use breadboard components. No Due Date Planned
#8
Production  version  depends on  Delivery of AGC subassy from Miteq.  Planned for Jan 1, 2005
#8
Production  version  depends on  Delivery of AGC subassy from Miteq.  Planned for Jan 1, 2005
#10
Production  version  depends on  Delivery of AGC subassy from Miteq.  Planned for Jan 1, 2005
#11
Production  version  depends on  Delivery of AGC subassy from Miteq.  Planned for Jan 1, 2005

Notes:

L302 50 pin filtered connector changed to fix slot ID problem.