Oct 13, 2004

L301 Status

Done
Pending
Late

#1
Functioning Normally, installed in antenna 13.  (Breadboard-in-a-box version)
#2
Functioning Normally, installed in antenna 13. (Hybrid version 1/2 Production / 1/2 Discrete RF section)
#3
Construction complete.  Testing and calibrating. (Hybrid version 1/2 Production / 1/2 Discrete RF section)
#4
Under Construction in LO lab, delayed due to parts delivery (Norden) to Oct 22nd (Hybrid version 1/2 Production / 1/2 Discrete RF section)
#5
Production  version  depends on  Delivery of AGC subassy from Miteq.  Planned for Jan 1, 2005
#6
Production  version  depends on  Delivery of AGC subassy from Miteq.  Planned for Jan 1, 2005
#0
Construction planned for Ready Service Spare as parts become available, possibly use breadboard components. No Due Date Planned.  Use in test rack.


L302 Status


#1
Functioning Normally, Installed in antenna 13.  No tuning restrictions.  Main DDS sample output added for phase testing. (Breadboard-in-a-box version)
#2
Functioning Normally, Installed in test rack.  No tuning restrictions. Main DDS sample output added for phase testing. (Breadboard-in-a-box version)
#3
Installed in test rack.  Digital Testing Only.  RF Section disabled. (Hybrid version 1/2 Production / 1/2 Discrete RF section)
#4
Functioning Normally, in use in synth lab as stable design reference. (Hybrid version 1/2 Production / 1/2 Discrete RF section)
#5
Testing and calibrating in LO-IF Lab(Hybrid version 1/2 Production / 1/2 Discrete RF section)
#6
Under Construction in LO lab, (Hybrid version 1/2 Production / 1/2 Discrete RF section)
#7
Production  version  depends on  Delivery of AGC subassy from Miteq.  Planned for Jan 1, 2005
#8
Production  version  depends on  Delivery of AGC subassy from Miteq.  Planned for Jan 1, 2005
#9
Production  version  depends on  Delivery of AGC subassy from Miteq.  Planned for Jan 1, 2005
#10
Production  version  depends on  Delivery of AGC subassy from Miteq.  Planned for Jan 1, 2005
#0
Construction planned for Ready Service Spare as parts become available, possibly use breadboard components. No Due Date Planned.  Use in test rack.

Notes:

L302-1 and L302-2 are limited to 2 telnet sessions until MIB stack problems are resolved.