21oct03 DSS Testing Timeline Summary Preliminary ALMA Offline Software Test Plan: -------------------------------------------- 31jan03 PhItst ** Offline: Phase I testing of AIPS++ complete 01mar03 PhIItst ** Offline: Phase II testing of AIPS++ complete 15mar03 PDR Preliminary Design Review 01may03 R0 Subsystem pre-release software ready (No AIPS++ software delivery here) 15jun03 TstPln ** Offline: Integrated testing & development plan ready 15jun03 CDR1 1st incremental Critical Design Review 01oct03 ** AIPS++ Proof-of concept ready by R1.0 - ACS/Python only 01oct03 R1 1st full Subsystem Release 1.0 01dec03 IR1 1st Integrated subsystem Release 01jan04 OpsPln ALMA Operations Plan ready (Software Development) 01jan04 TST1 ** Offline TESTING start Report & Audit update available by 15feb04 for CDR2 01apr04 R1.1 Subsystem Release 1.1 01may04 CDR2 2nd incremental CDR 01jul04 TST2 ** Offline TESTING start Report & Audit update available by 15aug04 01oct04 ** Offline: Some Core Engines available by R2 (2 stage release) 01oct04 R2 2nd Subsystem Release 2.0 01dec04 IR2 2nd Integrated subsystem Release 01jan05 TST3 ** Offline TESTING start (Core Engines available) Report & Audit update available by 15feb05 for CDR3 01apr05 ** Offline: All Core Engines available by R2.1 01apr05 R2.1 Subsystem Release 2.1 01may05 CDR3 3rd incremental CDR 01jul05 TST4 ** Offline TESTING start Report & Audit update available by 15aug05 01oct05 ** Offline: All Engines available by R3 01oct05 ** Offline: Simulator available by R3 01oct05 R3 3rd Subsystem Release 3.0 01dec05 IR3 3rd Integrated subsystem Release 01jan06 TST5 ** Offline TESTING start (All Engines available) Report & Audit update available by 15feb06 for CDR3 01apr06 ** Offline: All Engines available by R3.1 01apr06 ** Offline: Simulator available by R3.1 01apr06 ** Offline: All Priority 1's & most Priority 2's addressed. 01apr06 R3.1 Subsystem Release 3.1 01jun06 RR System Readiness Review 01jul06 TST6 ** Offline TESTING start (All Engines available) Report & Audit update available by 15aug06 01oct06 R4 4th Subsystem Release 4.0 01dec06 IR4 4th Integrated subsystem Release 01dec06 PAR Subsystem Preliminary Acceptance Review 01jan07 TST7 ** Offline TESTING start (All Engines available): Report & Audit update available by 01mar07 for CPA 01mar07 CPA Computing Preliminary Acceptance Review 01jun07 IntSci Interim Science Operations begins