ALMA |
 |
ALMA Software Test Plan development
Note: All test plans are drafts, more details are provided for near
term tests, less for those scheduled in the future. Plans will be
updated as near term tests are completed and later tests can be
defined better.
TestSchedule.template.mpp
Template Microsoft Project Gantt chart. This has relavent
release dates and design review milestones, and a couple of test
blocks. Feel free to down load this template to create a
subsystem test schedule.
TestSchedule.template.pdf
pdf version of the Test Schedule template.
Master Test Schedule (all subsystems included)
Master.TestSchedule.pdf
Gantt Chart showing all tests scheduled as of 17par04,
major and minor integration schedule and ALMA milestones.
Integration, Test, & Support
ITS.TestSchedule15sep03.pdf
DRAFT - Gantt Chart showing major and minor integration
schedule and ALMA milestones.
A Note to subsystems:
If you need
to test software after it has been integrated, then use this
chart to figure out when the software will be ready to
test. See also
http://www.aoc.nrao.edu/~dshepher/alma/usecases/ITS.UC.html for
a description of how ITS will integrate software from each
subsystem, what is expected, and how it will be tested.
Archive Subsystem:
Archive.TestPlan3nov03.txt
- Draft test plan for first tests. Some
issues unresolved.
Archive.TestSchedule.pdf
Gantt chart showing proposed schedule for first 3 tests as
well as when the Archive releases are.
Control Software Subsystem:
Control.TestPlan.txt
Draft test plan. 13nov03
Control.TestSchedule.pdf
Gantt chart of test schedule
Correlator Software Subsystem:
Correlator.TestPlan5nov03.txt
Test plan, 5nov03
Correlator.TestSchedule.pdf
Gantt chart showing proposed schedule
Executive Software Subsystem:
Exec.TestPlan.txt
Test Plan 11nov03
Exec.TestSchedule.pdf
- Gantt chart with proposed schedule
Observing Preparation Subsystem:
ObsPrep.TestPlan.txt
Test Plan describing tests for R1 and R1.1. Plan updated
on 8jul04 adding details about August 2004 tests.
ObsPrep.TestSchedule31oct03.pdf
Gantt Chart showing proposed test schedule and ALMA
milestones.
Offline Subsystem:
Offline.TestPlan21oct03.txt
Test Plan discussing time line of when tests will be
conducted in relation to major ALMA milestones.
Offline.TestSchedule7apr03.pdf
Gantt Chart showing proposed test schedule and ALMA
milestones.
Offline.TestCases7apr03.txt
Brief description of Test cases (Use Case subsets) that will be
exercised in each test.
Pipeline Subsystem:
Pipeline.TestPlan29aug03.txt
Test Plan discussing timeline, scope.
Pipeline.FirstUserTest15jan04.txt
Detailed description of the proto-pipeline first user
test scheduled for apr04.
Pipeline.SecondUserTest10jun04.txt
Detailed description of the proto-pipeline second user
test scheduled for August 2004. Focus is on flagging heuristics
tests.
Pipeline.TestSched2sep03.pdf
Gantt Chart showing proposed test schedule and ALMA
milestones.
Scheduling Subsystem:
Sched.TestPlan22sep03.txt
DRAFT Test plan discussing timeline and
scope. Initial outlines
of tests 1 & 2 are also presented.
Sched.TestSchedule22sep03.pdf
DRAFT Gantt Chart showing proposed test
schedule and ALMA
milestones.
Telescope Calibration Subsystem:
TelCal.TestPlan.txt
10nov03: Plan and Schedule
TelCal.TestSchedule24sep03.mpp
DRAFT Gantt chart showing proposed schedule, MSProject
format
TelCal.TestSchedule24sep03.pdf
DRAFT Gantt chart showing proposed schedule