Project Start Date: Thu 08/01/02
Project Finish Date: Wed 02/11/04
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
|---|---|---|---|---|---|---|
| 1 | MIB footprint available | 0 days | Fri 08/09/02 | Fri 08/09/02 | 0% | |
| 2 | ||||||
| 3 | Systems software ported to TriBoard | 0 days | Wed 09/18/02 | Wed 09/18/02 | 0% | |
| 4 | ||||||
| 5 | MIB board layout | 5.6 wks? | Mon 08/26/02 | Wed 10/02/02 | 0% | |
| 6 | MIB parts order & delivery | 6 wks? | Thu 09/12/02 | Wed 10/23/02 | 0% | |
| 7 | Order MIB PC board | 0 days | Wed 10/02/02 | Wed 10/02/02 | 0% | |
| 8 | MIB PC board in house | 0 days | Wed 10/23/02 | Wed 10/23/02 | 0% | |
| 9 | ||||||
| 10 | Overall M&C software arch & design | 17 wks? | Tue 09/10/02 | Mon 01/06/03 | 0% | |
| 11 | EVLA Advisory Comm meets | 0 days | Mon 12/16/02 | Mon 12/16/02 | 0% | |
| 12 | ||||||
| 13 | MIB software dev toolset licensed | 0 days | Fri 09/13/02 | Fri 09/13/02 | 0% | |
| 14 | MIB communication protocol specified | 0 days | Fri 09/13/02 | Fri 09/13/02 | 0% | |
| 15 | MIB comm protocol, test & dev (TriBoard) | 11 wks? | Mon 09/16/02 | Fri 11/29/02 | 0% | |
| 16 | Install & test MIB simulation env | 3.8 wks? | Tue 09/17/02 | Fri 10/11/02 | 0% | |
| 17 | MIB technician/engnr screens | 12.8 wks? | Mon 10/07/02 | Thu 01/02/03 | 0% | |
| 18 | ||||||
| 19 | MIB prototype board, design & dev | 12.6 wks? | Wed 10/02/02 | Mon 12/30/02 | 0% | |
| 20 | Begin design & dev | 0 days | Wed 10/02/02 | Wed 10/02/02 | 0% | |
| 21 | MIB prototype, Assembly/Test | 3.2 wks? | Thu 10/24/02 | Thu 11/14/02 | 0% | |
| 22 | MIB prototype board available | 0 days | Thu 11/14/02 | Thu 11/14/02 | 0% | |
| 23 | Design & dev completed | 0 days | Mon 12/30/02 | Mon 12/30/02 | 0% | |
| 24 | ||||||
| 25 | Systems software ported to MIB prototype board | 21 days? | Fri 11/15/02 | Fri 12/13/02 | 0% | |
| 26 | MIB comm protocol ported to MIB prototype board | 3 wks? | Mon 12/16/02 | Fri 01/03/03 | 0% | |
| 27 | ||||||
| 28 | MIB module/device software | 17 wks? | Fri 12/06/02 | Thu 04/03/03 | 0% | |
| 29 | MIB prototype with modules, test/eval | 20.8 wks? | Fri 12/06/02 | Wed 04/30/03 | 0% | |
| 30 | Build MIB boards for test antenna | 17 wks? | Thu 01/02/03 | Wed 04/30/03 | 0% | |
| 31 | MIB prototype with all devices, bench test | 17 wks? | Thu 01/02/03 | Wed 04/30/03 | 0% | |
| 32 | ||||||
| 33 | Overall design for hybrid array control | 13 wks? | Mon 01/13/03 | Fri 04/11/03 | 0% | |
| 34 | Hybrid array sftwre, for test ant on master pad | 15 wks? | Wed 02/26/03 | Wed 06/11/03 | 0% | |
| 35 | Hybrid array sftwre, for test ant in the array | 21 wks? | Tue 03/25/03 | Mon 08/18/03 | 0% | |
| 36 | Configure & purchase test ant & hybrid array real-time crates | 8 wks? | Wed 02/19/03 | Wed 04/16/03 | 0% | |
| 37 | Install test ant & hybrid array rt crates | 8 wks? | Wed 04/16/03 | Wed 06/11/03 | 0% | |
| 38 | ||||||
| 39 | Test antenna monitor data archive | 21 wks? | Thu 01/16/03 | Wed 06/11/03 | 0% | |
| 40 | ||||||
| 41 | Test Antenna | 33.4 wks? | Tue 04/01/03 | Wed 11/19/03 | 0% | |
| 42 | Test antenna into antenna barn | 0 days | Tue 04/01/03 | Tue 04/01/03 | 0% | |
| 43 | Test antenna outfitting, barn & master pad | 10.2 wks? | Tue 04/01/03 | Tue 06/10/03 | 0% | |
| 44 | Test antenna, master pad tests | 8.8 wks? | Wed 06/11/03 | Mon 08/11/03 | 0% | |
| 45 | Test antenna moved into array | 0 days | Mon 08/18/03 | Mon 08/18/03 | 0% | |
| 46 | Test antenna, array tests | 13.4 wks? | Tue 08/19/03 | Wed 11/19/03 | 0% | |
| 47 | ||||||
| 48 | Revisions to MIB design | 9 wks? | Tue 10/07/03 | Mon 12/08/03 | 0% | |
| 49 | ||||||
| 50 | Install AOC-based bench test networks | 8 wks? | Fri 09/20/02 | Thu 11/14/02 | 0% | |
| 51 | Install site-based bench test network | 8 wks? | Tue 02/04/03 | Tue 04/01/03 | 0% | |
| 52 | Install M&C network: contrl bldg & master pad | 15 wks? | Tue 12/17/02 | Tue 04/01/03 | 0% | |
| 53 | EVLA M&C network: test antenna array pad(s) | 21 wks? | Tue 03/25/03 | Mon 08/18/03 | 0% | |
| 54 | ||||||
| 55 | Begin outfitting 2nd test antenna | 0 days | Wed 02/11/04 | Wed 02/11/04 | 0% |
| ID | Name | Group | Max Units | Peak Units |
|---|
| Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
|---|