Project Start Date: Tue 05/01/01
Project Finish Date: Mon 05/03/10
ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
---|---|---|---|---|---|---|
1 | EVLA, t0 | 0 days | Tue 05/01/01 | Tue 05/01/01 | 0% | |
2 | ||||||
3 | 6.10.20 M&C EVLA Software | 462.6 wks | Tue 05/01/01 | Mon 05/03/10 | 4% | |
4 | ||||||
5 | Initial Budget, Labor Requirements & Schedule | 10 wks | Tue 06/05/01 | Mon 08/13/01 | 100% | |
6 | ||||||
7 | 6.10.20.05 Stabilization of the VLA | 89.4 wks | Tue 05/01/01 | Mon 01/27/03 | 36% | |
8 | Modcomp to Modcomp Replacement | 36.8 wks | Tue 05/01/01 | Wed 01/16/02 | 100% | |
9 | Prep - space, power, other | 4.5 wks | Tue 05/01/01 | Thu 05/31/01 | 100% | |
10 | Purchase Order Issued | 0 days | Fri 07/13/01 | Fri 07/13/01 | 100% | |
11 | Delivery (14 to 35 days ARO) | 0 days | Fri 09/28/01 | Fri 09/28/01 | 100% | |
12 | System Cabling, Load OS | 2 days | Wed 10/24/01 | Thu 10/25/01 | 100% | |
13 | System Config, Test Appl Software | 8 wks | Thu 10/25/01 | Wed 12/19/01 | 100% | |
14 | Switchover to New CPUs | 3 days | Mon 01/14/02 | Wed 01/16/02 | 100% | |
15 | Alternative to 9-Track Tape | 12 wks | Mon 02/04/02 | Fri 04/26/02 | 0% | |
16 | Correlator Controller Upgrade | 72 wks | Tue 05/01/01 | Mon 01/27/03 | 30% | |
17 | ||||||
18 | 6.10.20.10 Requirements (High Level, Raw) | 36.6 wks | Fri 10/05/01 | Fri 06/21/02 | 17% | |
19 | Engineering | 22.75 wks | Fri 10/05/01 | Mon 03/18/02 | 38% | |
20 | 1st draft | 6 wks | Fri 10/05/01 | Thu 11/15/01 | 100% | |
21 | comments | 2 wks | Fri 11/16/01 | Thu 11/29/01 | 0% | |
22 | 2nd draft | 8 wks | Mon 01/21/02 | Mon 03/18/02 | 0% | |
23 | Operations | 22.75 wks | Fri 10/05/01 | Mon 03/18/02 | 38% | |
24 | 1st draft | 6 wks | Fri 10/05/01 | Thu 11/15/01 | 100% | |
25 | comments | 2 wks | Fri 11/16/01 | Thu 11/29/01 | 0% | |
26 | 2nd draft | 8 wks | Mon 01/21/02 | Mon 03/18/02 | 0% | |
27 | Correlator Backend | 21 wks | Mon 01/07/02 | Fri 05/31/02 | 0% | |
28 | Fill vacany, Correl Backend | 0 days | Mon 01/07/02 | Mon 01/07/02 | 100% | |
29 | 1st draft | 10 wks | Mon 01/07/02 | Fri 03/15/02 | 0% | |
30 | comments | 3 wks | Mon 03/18/02 | Fri 04/05/02 | 0% | |
31 | 2nd draft | 8 wks | Mon 04/08/02 | Fri 05/31/02 | 0% | |
32 | Correlator M & C | 18 wks | Mon 02/18/02 | Fri 06/21/02 | 0% | |
33 | Fill vacancy, Correl M&C | 0 wks | Mon 02/18/02 | Mon 02/18/02 | 0% | |
34 | 1st draft | 8 wks | Mon 02/18/02 | Fri 04/12/02 | 0% | |
35 | comments | 2 wks | Mon 04/15/02 | Fri 04/26/02 | 0% | |
36 | 2nd draft | 8 wks | Mon 04/29/02 | Fri 06/21/02 | 0% | |
37 | High Level (Raw) Requirements complete | 0 wks | Fri 06/21/02 | Fri 06/21/02 | 0% | |
38 | ||||||
39 | 6.10.20.15 High Level Sftwre Arch & Design | 26.35 wks | Fri 01/04/02 | Mon 07/08/02 | 0% | |
40 | MIB processor & RTOS selection | 6 wks | Fri 01/04/02 | Thu 02/14/02 | 0% | |
41 | Antenna M&C Initial Design | 10 wks | Fri 01/18/02 | Thu 03/28/02 | 0% | |
42 | Preparation for M&C Antenna Hardware PDR | 2 wks | Fri 03/01/02 | Thu 03/14/02 | 0% | |
43 | M&C Antenna Hardware PDR | 0 wks | Fri 03/15/02 | Fri 03/15/02 | 0% | |
44 | PDR Analysis & Revision | 2 wks | Fri 03/15/02 | Thu 03/28/02 | 0% | |
45 | User Interface, Prototypical Screens | 4 wks | Mon 03/18/02 | Mon 04/15/02 | 0% | |
46 | System Timing, Initial Specifications | 8 wks | Fri 03/29/02 | Thu 05/23/02 | 0% | |
47 | Transition Planning | 8 wks | Mon 01/21/02 | Fri 05/03/02 | 0% | |
48 | CMP testbed (VLA M&C, Hybrid Array) | 12 wks | Mon 04/15/02 | Mon 07/08/02 | 0% | |
49 | e2e interface discussions | 2 wks | Mon 03/25/02 | Tue 05/14/02 | 0% | |
50 | Preparation for M&C Software PDR | 2 wks | Wed 05/01/02 | Tue 05/14/02 | 0% | |
51 | M&C Software PDR | 0 wks | Wed 05/15/02 | Wed 05/15/02 | 0% | |
52 | PDR Analysis & Revision | 2 wks | Wed 05/15/02 | Tue 05/28/02 | 0% | |
53 | ||||||
54 | 6.10.20.20 Tst & Dev Support, Enhncd Ants | 41 wks | Fri 03/15/02 | Thu 01/02/03 | 0% | |
55 | Task Specifications | 8 wks | Fri 03/15/02 | Thu 05/30/02 | 0% | |
56 | Software Development | 38 wks | Fri 04/05/02 | Thu 01/02/03 | 0% | |
57 | Test & Dev Spprt for Enhanced Ants Rdy | 0 days | Thu 01/02/03 | Thu 01/02/03 | 0% | |
58 | ||||||
59 | 6.10.20.25 Mid-Level Analysis & Design | 67.6 wks | Tue 05/01/01 | Tue 08/20/02 | 0% | |
60 | Fill vacancy, Gen'l OOA/D/P | 0 wks | Mon 03/04/02 | Mon 03/04/02 | 0% | |
61 | Detailed (Well-Formed) Requirements | 63.6 wks | Tue 05/01/01 | Tue 07/23/02 | 0% | |
62 | Scientific | 8 wks | Wed 05/29/02 | Tue 07/23/02 | 0% | |
63 | Engineering | 8 wks | Wed 05/29/02 | Tue 07/23/02 | 0% | |
64 | Operations | 8 wks | Wed 05/29/02 | Tue 07/23/02 | 0% | |
65 | Correlator (M&C, Backend) | 8 wks | Tue 05/01/01 | Mon 06/25/01 | 0% | |
66 | e2e IF Specifications | 8.6 wks | Wed 05/29/02 | Fri 07/26/02 | 0% | |
67 | Observation Scheduling Software | 4 wks | Wed 05/29/02 | Tue 06/25/02 | 0% | |
68 | Data Archive Requirements | 4 wks | Wed 05/29/02 | Tue 06/25/02 | 0% | |
69 | Image Pipeline Requirements | 4 wks | Wed 05/29/02 | Tue 06/25/02 | 0% | |
70 | Preparation for e2e PDR, M&C Interfaces | 2 wks | Mon 07/01/02 | Fri 07/12/02 | 0% | |
71 | e2e PDR, M&C Interfaces | 0 wks | Mon 07/15/02 | Mon 07/15/02 | 0% | |
72 | PDR Analysis & Revision | 2 wks | Mon 07/15/02 | Fri 07/26/02 | 0% | |
73 | Fill vacancy, Astronomy Appls | 0 wks | Mon 04/01/02 | Mon 04/01/02 | 0% | |
74 | Observing Layer | 10 wks | Mon 04/01/02 | Fri 06/07/02 | 0% | |
75 | System Timing | 8 wks | Wed 05/29/02 | Tue 07/23/02 | 0% | |
76 | Scan Setup & Supervision | 6 wks | Wed 05/29/02 | Tue 07/09/02 | 0% | |
77 | Antenna Control | 8 wks | Wed 05/29/02 | Tue 07/23/02 | 0% | |
78 | Monitor Data | 8 wks | Wed 05/29/02 | Tue 07/23/02 | 0% | |
79 | Hybrid Array Operation | 12 wks | Wed 05/29/02 | Tue 08/20/02 | 0% | |
80 | ||||||
81 | Preparation for System CDR | 2 wks | Wed 05/01/02 | Tue 05/14/02 | 0% | |
82 | Monitor & Control System CDR | 0 wks | Wed 05/15/02 | Wed 05/15/02 | 0% | |
83 | Analysis & Revision | 8 wks | Wed 05/15/02 | Tue 07/09/02 | 0% | |
84 | ||||||
85 | 6.10.20.30 Test & Dev Support, Correlator | 188.2 wks | Mon 02/18/02 | Wed 10/12/05 | 0% | |
86 | Correl M&C, Correl Backend vacancies filled | 0 wks | Mon 02/18/02 | Mon 02/18/02 | 0% | |
87 | Training, Correl Arch (Penticton) | 10 wks | Mon 04/01/02 | Fri 06/07/02 | 0% | |
88 | Correlator Monitor & Control | 129.2 wks | Mon 06/10/02 | Mon 12/13/04 | 0% | |
89 | Virtual Correl Interface Specification | 16 wks | Mon 06/10/02 | Fri 09/27/02 | 0% | |
90 | Test Sftwre Interface Specification | 16 wks | Mon 09/30/02 | Fri 01/24/03 | 0% | |
91 | Device Driver Interface Specification | 16 wks | Mon 01/27/03 | Fri 05/16/03 | 0% | |
92 | Virtual Correl Sftwre Coding & Tsting | 40 wks | Mon 05/19/03 | Fri 02/27/04 | 0% | |
93 | Test Sftwre Coding & Testing | 26 wks | Mon 03/01/04 | Fri 08/27/04 | 0% | |
94 | Correlator board manuals available | 0 wks | Tue 06/15/04 | Tue 06/15/04 | 0% | |
95 | Device Driver Sftwre Coding & Testing | 26 wks | Tue 06/15/04 | Mon 12/13/04 | 0% | |
96 | Correlator PDR | 0 wks | Mon 09/02/02 | Mon 09/02/02 | 0% | |
97 | Correl Data Products - FFTs, Fits File Fragments | 139 wks | Mon 02/18/02 | Fri 10/29/04 | 0% | |
98 | Training, Correl Arch (Penticton) | 10 wks | Mon 02/18/02 | Fri 04/26/02 | 0% | |
99 | System Specification | 26 wks | Mon 09/30/02 | Fri 04/04/03 | 0% | |
100 | Coding & Testing | 56 wks | Mon 04/07/03 | Fri 05/07/04 | 0% | |
101 | FITS/AIPS++ Extensions | 25 wks | Mon 05/10/04 | Fri 10/29/04 | 0% | |
102 | System Integration & Testing, Penticton | 43 wks | Tue 12/14/04 | Wed 10/12/05 | 0% | |
103 | M&C System Rdy For WIDAR Correl Tst & Dev Support | 0 wks | Thu 12/01/05 | Thu 12/01/05 | 0% | |
104 | ||||||
105 | M&C System, Ready For Archive | 0 wks | Mon 04/17/06 | Mon 04/17/06 | 0% | |
106 | ||||||
107 | 6.10.20.35 Detailed Design & Coding | 386.2 wks | Wed 07/17/02 | Mon 01/25/10 | 0% | |
108 | Observing Layer | 52 wks | Wed 07/17/02 | Tue 07/22/03 | 0% | |
109 | Scan Setup & Supervision | 52 wks | Wed 01/22/03 | Tue 01/27/04 | 0% | |
110 | Antenna Control | 55 wks | Wed 07/17/02 | Tue 08/12/03 | 0% | |
111 | Full Support, Enhanced Antennas | 0 wks | Thu 04/08/04 | Thu 04/08/04 | 0% | |
112 | Monitor Data | 18 wks | Wed 07/17/02 | Tue 11/19/02 | 0% | |
113 | Warnings & Alarms | 26 wks | Wed 11/20/02 | Tue 05/27/03 | 0% | |
114 | Data Flagging | 26 wks | Wed 05/28/03 | Thu 11/27/03 | 0% | |
115 | Logging | 26 wks | Fri 11/28/03 | Tue 06/01/04 | 0% | |
116 | User Interfaces | 104 wks | Wed 07/17/02 | Tue 07/27/04 | 0% | |
117 | Hybrid Array support | 52 wks | Wed 07/17/02 | Tue 07/22/03 | 0% | |
118 | Correlator, at VLA Site | 152 wks | Mon 07/03/06 | Mon 06/15/09 | 0% | |
119 | Begin Installation of Correlator at VLA | 0 wks | Mon 07/03/06 | Mon 07/03/06 | 0% | |
120 | System Integration & Testing, VLA | 48 wks | Mon 07/31/06 | Wed 07/04/07 | 0% | |
121 | Preparation for Correl Observations | 23.5 wks | Thu 01/18/07 | Mon 07/02/07 | 0% | |
122 | Begin Correlator Test Observations | 0 wks | Wed 07/04/07 | Wed 07/04/07 | 0% | |
123 | Coding of Operational Sftwre, Correlator | 100 wks | Thu 07/05/07 | Mon 06/15/09 | 0% | |
124 | EVLA Correlator Operational | 0 wks | Mon 06/15/09 | Mon 06/15/09 | 0% | |
125 | VLA Correlator Shutdown | 0 wks | Mon 01/25/10 | Mon 01/25/10 | 0% | |
126 | Data Archive Interface | 39 wks | Tue 01/20/09 | Mon 10/19/09 | 0% | |
127 | Image Pipeline Interface | 39 wks | Tue 01/20/09 | Mon 10/19/09 | 0% | |
128 | ||||||
129 | Last Antenna Converted to EVLA Design | 0 wks | Mon 03/03/08 | Mon 03/03/08 | 0% | |
130 | ||||||
131 | Last New Receiver Installed | 0 wks | Mon 05/03/10 | Mon 05/03/10 | 0% | |
132 | ||||||
133 | EVLA Operational | 0 wks | Mon 05/03/10 | Mon 05/03/10 | 0% |
ID | Name | Group | Max Units | Peak Units |
---|---|---|---|---|
1 | 100% | 0% | ||
2 | 100% | 0% | ||
3 | 100% | 0% | ||
4 | 100% | 0% | ||
5 | 100% | 0% | ||
6 | 100% | 0% | ||
7 | 100% | 0% | ||
8 | 100% | 0% | ||
9 | 100% | 0% | ||
10 | 100% | 0% | ||
11 | 100% | 0% | ||
12 | 100% | 0% | ||
13 | 100% | 0% | ||
14 | 100% | 0% | ||
15 | 100% | 0% | ||
16 | 100% | 0% | ||
17 | 100% | 0% | ||
18 | 100% | 0% | ||
19 | 100% | 0% | ||
20 | 100% | 0% |
Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
---|