EVLA_MC


Project Start Date: Tue 05/01/01
Project Finish Date: Mon 05/03/10

Tasks

ID
Task Name
DurationStartFinishResource Names% Complete
1
EVLA, t0
0 daysTue 05/01/01Tue 05/01/01 0%
2      
3
6.10.20 M&C EVLA Software
462.6 wksTue 05/01/01Mon 05/03/10 4%
4      
5
Initial Budget, Labor Requirements & Schedule
10 wksTue 06/05/01Mon 08/13/01 100%
6      
7
6.10.20.05 Stabilization of the VLA
89.4 wksTue 05/01/01Mon 01/27/03 36%
8
Modcomp to Modcomp Replacement
36.8 wksTue 05/01/01Wed 01/16/02 100%
9
Prep - space, power, other
4.5 wksTue 05/01/01Thu 05/31/01 100%
10
Purchase Order Issued
0 daysFri 07/13/01Fri 07/13/01 100%
11
Delivery (14 to 35 days ARO)
0 daysFri 09/28/01Fri 09/28/01 100%
12
System Cabling, Load OS
2 daysWed 10/24/01Thu 10/25/01 100%
13
System Config, Test Appl Software
8 wksThu 10/25/01Wed 12/19/01 100%
14
Switchover to New CPUs
3 daysMon 01/14/02Wed 01/16/02 100%
15
Alternative to 9-Track Tape
12 wksMon 02/04/02Fri 04/26/02 0%
16
Correlator Controller Upgrade
72 wksTue 05/01/01Mon 01/27/03 30%
17      
18
6.10.20.10 Requirements (High Level, Raw)
36.6 wksFri 10/05/01Fri 06/21/02 17%
19
Engineering
22.75 wksFri 10/05/01Mon 03/18/02 38%
20
1st draft
6 wksFri 10/05/01Thu 11/15/01 100%
21
comments
2 wksFri 11/16/01Thu 11/29/01 0%
22
2nd draft
8 wksMon 01/21/02Mon 03/18/02 0%
23
Operations
22.75 wksFri 10/05/01Mon 03/18/02 38%
24
1st draft
6 wksFri 10/05/01Thu 11/15/01 100%
25
comments
2 wksFri 11/16/01Thu 11/29/01 0%
26
2nd draft
8 wksMon 01/21/02Mon 03/18/02 0%
27
Correlator Backend
21 wksMon 01/07/02Fri 05/31/02 0%
28
Fill vacany, Correl Backend
0 daysMon 01/07/02Mon 01/07/02 100%
29
1st draft
10 wksMon 01/07/02Fri 03/15/02 0%
30
comments
3 wksMon 03/18/02Fri 04/05/02 0%
31
2nd draft
8 wksMon 04/08/02Fri 05/31/02 0%
32
Correlator M & C
18 wksMon 02/18/02Fri 06/21/02 0%
33
Fill vacancy, Correl M&C
0 wksMon 02/18/02Mon 02/18/02 0%
34
1st draft
8 wksMon 02/18/02Fri 04/12/02 0%
35
comments
2 wksMon 04/15/02Fri 04/26/02 0%
36
2nd draft
8 wksMon 04/29/02Fri 06/21/02 0%
37
High Level (Raw) Requirements complete
0 wksFri 06/21/02Fri 06/21/02 0%
38      
39
6.10.20.15 High Level Sftwre Arch & Design
26.35 wksFri 01/04/02Mon 07/08/02 0%
40
MIB processor & RTOS selection
6 wksFri 01/04/02Thu 02/14/02 0%
41
Antenna M&C Initial Design
10 wksFri 01/18/02Thu 03/28/02 0%
42
Preparation for M&C Antenna Hardware PDR
2 wksFri 03/01/02Thu 03/14/02 0%
43
M&C Antenna Hardware PDR
0 wksFri 03/15/02Fri 03/15/02 0%
44
PDR Analysis & Revision
2 wksFri 03/15/02Thu 03/28/02 0%
45
User Interface, Prototypical Screens
4 wksMon 03/18/02Mon 04/15/02 0%
46
System Timing, Initial Specifications
8 wksFri 03/29/02Thu 05/23/02 0%
47
Transition Planning
8 wksMon 01/21/02Fri 05/03/02 0%
48
CMP testbed (VLA M&C, Hybrid Array)
12 wksMon 04/15/02Mon 07/08/02 0%
49
e2e interface discussions
2 wksMon 03/25/02Tue 05/14/02 0%
50
Preparation for M&C Software PDR
2 wksWed 05/01/02Tue 05/14/02 0%
51
M&C Software PDR
0 wksWed 05/15/02Wed 05/15/02 0%
52
PDR Analysis & Revision
2 wksWed 05/15/02Tue 05/28/02 0%
53      
54
6.10.20.20 Tst & Dev Support, Enhncd Ants
41 wksFri 03/15/02Thu 01/02/03 0%
55
Task Specifications
8 wksFri 03/15/02Thu 05/30/02 0%
56
Software Development
38 wksFri 04/05/02Thu 01/02/03 0%
57
Test & Dev Spprt for Enhanced Ants Rdy
0 daysThu 01/02/03Thu 01/02/03 0%
58      
59
6.10.20.25 Mid-Level Analysis & Design
67.6 wksTue 05/01/01Tue 08/20/02 0%
60
Fill vacancy, Gen'l OOA/D/P
0 wksMon 03/04/02Mon 03/04/02 0%
61
Detailed (Well-Formed) Requirements
63.6 wksTue 05/01/01Tue 07/23/02 0%
62
Scientific
8 wksWed 05/29/02Tue 07/23/02 0%
63
Engineering
8 wksWed 05/29/02Tue 07/23/02 0%
64
Operations
8 wksWed 05/29/02Tue 07/23/02 0%
65
Correlator (M&C, Backend)
8 wksTue 05/01/01Mon 06/25/01 0%
66
e2e IF Specifications
8.6 wksWed 05/29/02Fri 07/26/02 0%
67
Observation Scheduling Software
4 wksWed 05/29/02Tue 06/25/02 0%
68
Data Archive Requirements
4 wksWed 05/29/02Tue 06/25/02 0%
69
Image Pipeline Requirements
4 wksWed 05/29/02Tue 06/25/02 0%
70
Preparation for e2e PDR, M&C Interfaces
2 wksMon 07/01/02Fri 07/12/02 0%
71
e2e PDR, M&C Interfaces
0 wksMon 07/15/02Mon 07/15/02 0%
72
PDR Analysis & Revision
2 wksMon 07/15/02Fri 07/26/02 0%
73
Fill vacancy, Astronomy Appls
0 wksMon 04/01/02Mon 04/01/02 0%
74
Observing Layer
10 wksMon 04/01/02Fri 06/07/02 0%
75
System Timing
8 wksWed 05/29/02Tue 07/23/02 0%
76
Scan Setup & Supervision
6 wksWed 05/29/02Tue 07/09/02 0%
77
Antenna Control
8 wksWed 05/29/02Tue 07/23/02 0%
78
Monitor Data
8 wksWed 05/29/02Tue 07/23/02 0%
79
Hybrid Array Operation
12 wksWed 05/29/02Tue 08/20/02 0%
80      
81
Preparation for System CDR
2 wksWed 05/01/02Tue 05/14/02 0%
82
Monitor & Control System CDR
0 wksWed 05/15/02Wed 05/15/02 0%
83
Analysis & Revision
8 wksWed 05/15/02Tue 07/09/02 0%
84      
85
6.10.20.30 Test & Dev Support, Correlator
188.2 wksMon 02/18/02Wed 10/12/05 0%
86
Correl M&C, Correl Backend vacancies filled
0 wksMon 02/18/02Mon 02/18/02 0%
87
Training, Correl Arch (Penticton)
10 wksMon 04/01/02Fri 06/07/02 0%
88
Correlator Monitor & Control
129.2 wksMon 06/10/02Mon 12/13/04 0%
89
Virtual Correl Interface Specification
16 wksMon 06/10/02Fri 09/27/02 0%
90
Test Sftwre Interface Specification
16 wksMon 09/30/02Fri 01/24/03 0%
91
Device Driver Interface Specification
16 wksMon 01/27/03Fri 05/16/03 0%
92
Virtual Correl Sftwre Coding & Tsting
40 wksMon 05/19/03Fri 02/27/04 0%
93
Test Sftwre Coding & Testing
26 wksMon 03/01/04Fri 08/27/04 0%
94
Correlator board manuals available
0 wksTue 06/15/04Tue 06/15/04 0%
95
Device Driver Sftwre Coding & Testing
26 wksTue 06/15/04Mon 12/13/04 0%
96
Correlator PDR
0 wksMon 09/02/02Mon 09/02/02 0%
97
Correl Data Products - FFTs, Fits File Fragments
139 wksMon 02/18/02Fri 10/29/04 0%
98
Training, Correl Arch (Penticton)
10 wksMon 02/18/02Fri 04/26/02 0%
99
System Specification
26 wksMon 09/30/02Fri 04/04/03 0%
100
Coding & Testing
56 wksMon 04/07/03Fri 05/07/04 0%
101
FITS/AIPS++ Extensions
25 wksMon 05/10/04Fri 10/29/04 0%
102
System Integration & Testing, Penticton
43 wksTue 12/14/04Wed 10/12/05 0%
103
M&C System Rdy For WIDAR Correl Tst & Dev Support
0 wksThu 12/01/05Thu 12/01/05 0%
104      
105
M&C System, Ready For Archive
0 wksMon 04/17/06Mon 04/17/06 0%
106      
107
6.10.20.35 Detailed Design & Coding
386.2 wksWed 07/17/02Mon 01/25/10 0%
108
Observing Layer
52 wksWed 07/17/02Tue 07/22/03 0%
109
Scan Setup & Supervision
52 wksWed 01/22/03Tue 01/27/04 0%
110
Antenna Control
55 wksWed 07/17/02Tue 08/12/03 0%
111
Full Support, Enhanced Antennas
0 wksThu 04/08/04Thu 04/08/04 0%
112
Monitor Data
18 wksWed 07/17/02Tue 11/19/02 0%
113
Warnings & Alarms
26 wksWed 11/20/02Tue 05/27/03 0%
114
Data Flagging
26 wksWed 05/28/03Thu 11/27/03 0%
115
Logging
26 wksFri 11/28/03Tue 06/01/04 0%
116
User Interfaces
104 wksWed 07/17/02Tue 07/27/04 0%
117
Hybrid Array support
52 wksWed 07/17/02Tue 07/22/03 0%
118
Correlator, at VLA Site
152 wksMon 07/03/06Mon 06/15/09 0%
119
Begin Installation of Correlator at VLA
0 wksMon 07/03/06Mon 07/03/06 0%
120
System Integration & Testing, VLA
48 wksMon 07/31/06Wed 07/04/07 0%
121
Preparation for Correl Observations
23.5 wksThu 01/18/07Mon 07/02/07 0%
122
Begin Correlator Test Observations
0 wksWed 07/04/07Wed 07/04/07 0%
123
Coding of Operational Sftwre, Correlator
100 wksThu 07/05/07Mon 06/15/09 0%
124
EVLA Correlator Operational
0 wksMon 06/15/09Mon 06/15/09 0%
125
VLA Correlator Shutdown
0 wksMon 01/25/10Mon 01/25/10 0%
126
Data Archive Interface
39 wksTue 01/20/09Mon 10/19/09 0%
127
Image Pipeline Interface
39 wksTue 01/20/09Mon 10/19/09 0%
128      
129
Last Antenna Converted to EVLA Design
0 wksMon 03/03/08Mon 03/03/08 0%
130      
131
Last New Receiver Installed
0 wksMon 05/03/10Mon 05/03/10 0%
132      
133
EVLA Operational
0 wksMon 05/03/10Mon 05/03/10 0%

Resources

IDNameGroupMax UnitsPeak Units
1  100%0%
2  100%0%
3  100%0%
4  100%0%
5  100%0%
6  100%0%
7  100%0%
8  100%0%
9  100%0%
10  100%0%
11  100%0%
12  100%0%
13  100%0%
14  100%0%
15  100%0%
16  100%0%
17  100%0%
18  100%0%
19  100%0%
20  100%0%

Assignments

Task IDTask NameResource NameWorkStartFinish% Work Complete