Project Start Date: Tue 05/01/01
Project Finish Date: Mon 05/03/10
| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
|---|---|---|---|---|---|---|
| 1 | EVLA, t0 | 0 days | Tue 05/01/01 | Tue 05/01/01 | 0% | |
| 2 | ||||||
| 3 | 6.10.20 M&C EVLA Software | 462.6 wks | Tue 05/01/01 | Mon 05/03/10 | 4% | |
| 4 | ||||||
| 5 | Initial Budget, Labor Requirements & Schedule | 10 wks | Tue 06/05/01 | Mon 08/13/01 | 100% | |
| 6 | ||||||
| 7 | 6.10.20.05 Stabilization of the VLA | 89.4 wks | Tue 05/01/01 | Mon 01/27/03 | 36% | |
| 8 | Modcomp to Modcomp Replacement | 36.8 wks | Tue 05/01/01 | Wed 01/16/02 | 100% | |
| 9 | Prep - space, power, other | 4.5 wks | Tue 05/01/01 | Thu 05/31/01 | 100% | |
| 10 | Purchase Order Issued | 0 days | Fri 07/13/01 | Fri 07/13/01 | 100% | |
| 11 | Delivery (14 to 35 days ARO) | 0 days | Fri 09/28/01 | Fri 09/28/01 | 100% | |
| 12 | System Cabling, Load OS | 2 days | Wed 10/24/01 | Thu 10/25/01 | 100% | |
| 13 | System Config, Test Appl Software | 8 wks | Thu 10/25/01 | Wed 12/19/01 | 100% | |
| 14 | Switchover to New CPUs | 3 days | Mon 01/14/02 | Wed 01/16/02 | 100% | |
| 15 | Alternative to 9-Track Tape | 12 wks | Mon 02/04/02 | Fri 04/26/02 | 0% | |
| 16 | Correlator Controller Upgrade | 72 wks | Tue 05/01/01 | Mon 01/27/03 | 30% | |
| 17 | ||||||
| 18 | 6.10.20.10 Requirements (High Level, Raw) | 36.6 wks | Fri 10/05/01 | Fri 06/21/02 | 17% | |
| 19 | Engineering | 22.75 wks | Fri 10/05/01 | Mon 03/18/02 | 38% | |
| 20 | 1st draft | 6 wks | Fri 10/05/01 | Thu 11/15/01 | 100% | |
| 21 | comments | 2 wks | Fri 11/16/01 | Thu 11/29/01 | 0% | |
| 22 | 2nd draft | 8 wks | Mon 01/21/02 | Mon 03/18/02 | 0% | |
| 23 | Operations | 22.75 wks | Fri 10/05/01 | Mon 03/18/02 | 38% | |
| 24 | 1st draft | 6 wks | Fri 10/05/01 | Thu 11/15/01 | 100% | |
| 25 | comments | 2 wks | Fri 11/16/01 | Thu 11/29/01 | 0% | |
| 26 | 2nd draft | 8 wks | Mon 01/21/02 | Mon 03/18/02 | 0% | |
| 27 | Correlator Backend | 21 wks | Mon 01/07/02 | Fri 05/31/02 | 0% | |
| 28 | Fill vacany, Correl Backend | 0 days | Mon 01/07/02 | Mon 01/07/02 | 100% | |
| 29 | 1st draft | 10 wks | Mon 01/07/02 | Fri 03/15/02 | 0% | |
| 30 | comments | 3 wks | Mon 03/18/02 | Fri 04/05/02 | 0% | |
| 31 | 2nd draft | 8 wks | Mon 04/08/02 | Fri 05/31/02 | 0% | |
| 32 | Correlator M & C | 18 wks | Mon 02/18/02 | Fri 06/21/02 | 0% | |
| 33 | Fill vacancy, Correl M&C | 0 wks | Mon 02/18/02 | Mon 02/18/02 | 0% | |
| 34 | 1st draft | 8 wks | Mon 02/18/02 | Fri 04/12/02 | 0% | |
| 35 | comments | 2 wks | Mon 04/15/02 | Fri 04/26/02 | 0% | |
| 36 | 2nd draft | 8 wks | Mon 04/29/02 | Fri 06/21/02 | 0% | |
| 37 | High Level (Raw) Requirements complete | 0 wks | Fri 06/21/02 | Fri 06/21/02 | 0% | |
| 38 | ||||||
| 39 | 6.10.20.15 High Level Sftwre Arch & Design | 26.35 wks | Fri 01/04/02 | Mon 07/08/02 | 0% | |
| 40 | MIB processor & RTOS selection | 6 wks | Fri 01/04/02 | Thu 02/14/02 | 0% | |
| 41 | Antenna M&C Initial Design | 10 wks | Fri 01/18/02 | Thu 03/28/02 | 0% | |
| 42 | Preparation for M&C Antenna Hardware PDR | 2 wks | Fri 03/01/02 | Thu 03/14/02 | 0% | |
| 43 | M&C Antenna Hardware PDR | 0 wks | Fri 03/15/02 | Fri 03/15/02 | 0% | |
| 44 | PDR Analysis & Revision | 2 wks | Fri 03/15/02 | Thu 03/28/02 | 0% | |
| 45 | User Interface, Prototypical Screens | 4 wks | Mon 03/18/02 | Mon 04/15/02 | 0% | |
| 46 | System Timing, Initial Specifications | 8 wks | Fri 03/29/02 | Thu 05/23/02 | 0% | |
| 47 | Transition Planning | 8 wks | Mon 01/21/02 | Fri 05/03/02 | 0% | |
| 48 | CMP testbed (VLA M&C, Hybrid Array) | 12 wks | Mon 04/15/02 | Mon 07/08/02 | 0% | |
| 49 | e2e interface discussions | 2 wks | Mon 03/25/02 | Tue 05/14/02 | 0% | |
| 50 | Preparation for M&C Software PDR | 2 wks | Wed 05/01/02 | Tue 05/14/02 | 0% | |
| 51 | M&C Software PDR | 0 wks | Wed 05/15/02 | Wed 05/15/02 | 0% | |
| 52 | PDR Analysis & Revision | 2 wks | Wed 05/15/02 | Tue 05/28/02 | 0% | |
| 53 | ||||||
| 54 | 6.10.20.20 Tst & Dev Support, Enhncd Ants | 41 wks | Fri 03/15/02 | Thu 01/02/03 | 0% | |
| 55 | Task Specifications | 8 wks | Fri 03/15/02 | Thu 05/30/02 | 0% | |
| 56 | Software Development | 38 wks | Fri 04/05/02 | Thu 01/02/03 | 0% | |
| 57 | Test & Dev Spprt for Enhanced Ants Rdy | 0 days | Thu 01/02/03 | Thu 01/02/03 | 0% | |
| 58 | ||||||
| 59 | 6.10.20.25 Mid-Level Analysis & Design | 67.6 wks | Tue 05/01/01 | Tue 08/20/02 | 0% | |
| 60 | Fill vacancy, Gen'l OOA/D/P | 0 wks | Mon 03/04/02 | Mon 03/04/02 | 0% | |
| 61 | Detailed (Well-Formed) Requirements | 63.6 wks | Tue 05/01/01 | Tue 07/23/02 | 0% | |
| 62 | Scientific | 8 wks | Wed 05/29/02 | Tue 07/23/02 | 0% | |
| 63 | Engineering | 8 wks | Wed 05/29/02 | Tue 07/23/02 | 0% | |
| 64 | Operations | 8 wks | Wed 05/29/02 | Tue 07/23/02 | 0% | |
| 65 | Correlator (M&C, Backend) | 8 wks | Tue 05/01/01 | Mon 06/25/01 | 0% | |
| 66 | e2e IF Specifications | 8.6 wks | Wed 05/29/02 | Fri 07/26/02 | 0% | |
| 67 | Observation Scheduling Software | 4 wks | Wed 05/29/02 | Tue 06/25/02 | 0% | |
| 68 | Data Archive Requirements | 4 wks | Wed 05/29/02 | Tue 06/25/02 | 0% | |
| 69 | Image Pipeline Requirements | 4 wks | Wed 05/29/02 | Tue 06/25/02 | 0% | |
| 70 | Preparation for e2e PDR, M&C Interfaces | 2 wks | Mon 07/01/02 | Fri 07/12/02 | 0% | |
| 71 | e2e PDR, M&C Interfaces | 0 wks | Mon 07/15/02 | Mon 07/15/02 | 0% | |
| 72 | PDR Analysis & Revision | 2 wks | Mon 07/15/02 | Fri 07/26/02 | 0% | |
| 73 | Fill vacancy, Astronomy Appls | 0 wks | Mon 04/01/02 | Mon 04/01/02 | 0% | |
| 74 | Observing Layer | 10 wks | Mon 04/01/02 | Fri 06/07/02 | 0% | |
| 75 | System Timing | 8 wks | Wed 05/29/02 | Tue 07/23/02 | 0% | |
| 76 | Scan Setup & Supervision | 6 wks | Wed 05/29/02 | Tue 07/09/02 | 0% | |
| 77 | Antenna Control | 8 wks | Wed 05/29/02 | Tue 07/23/02 | 0% | |
| 78 | Monitor Data | 8 wks | Wed 05/29/02 | Tue 07/23/02 | 0% | |
| 79 | Hybrid Array Operation | 12 wks | Wed 05/29/02 | Tue 08/20/02 | 0% | |
| 80 | ||||||
| 81 | Preparation for System CDR | 2 wks | Wed 05/01/02 | Tue 05/14/02 | 0% | |
| 82 | Monitor & Control System CDR | 0 wks | Wed 05/15/02 | Wed 05/15/02 | 0% | |
| 83 | Analysis & Revision | 8 wks | Wed 05/15/02 | Tue 07/09/02 | 0% | |
| 84 | ||||||
| 85 | 6.10.20.30 Test & Dev Support, Correlator | 188.2 wks | Mon 02/18/02 | Wed 10/12/05 | 0% | |
| 86 | Correl M&C, Correl Backend vacancies filled | 0 wks | Mon 02/18/02 | Mon 02/18/02 | 0% | |
| 87 | Training, Correl Arch (Penticton) | 10 wks | Mon 04/01/02 | Fri 06/07/02 | 0% | |
| 88 | Correlator Monitor & Control | 129.2 wks | Mon 06/10/02 | Mon 12/13/04 | 0% | |
| 89 | Virtual Correl Interface Specification | 16 wks | Mon 06/10/02 | Fri 09/27/02 | 0% | |
| 90 | Test Sftwre Interface Specification | 16 wks | Mon 09/30/02 | Fri 01/24/03 | 0% | |
| 91 | Device Driver Interface Specification | 16 wks | Mon 01/27/03 | Fri 05/16/03 | 0% | |
| 92 | Virtual Correl Sftwre Coding & Tsting | 40 wks | Mon 05/19/03 | Fri 02/27/04 | 0% | |
| 93 | Test Sftwre Coding & Testing | 26 wks | Mon 03/01/04 | Fri 08/27/04 | 0% | |
| 94 | Correlator board manuals available | 0 wks | Tue 06/15/04 | Tue 06/15/04 | 0% | |
| 95 | Device Driver Sftwre Coding & Testing | 26 wks | Tue 06/15/04 | Mon 12/13/04 | 0% | |
| 96 | Correlator PDR | 0 wks | Mon 09/02/02 | Mon 09/02/02 | 0% | |
| 97 | Correl Data Products - FFTs, Fits File Fragments | 139 wks | Mon 02/18/02 | Fri 10/29/04 | 0% | |
| 98 | Training, Correl Arch (Penticton) | 10 wks | Mon 02/18/02 | Fri 04/26/02 | 0% | |
| 99 | System Specification | 26 wks | Mon 09/30/02 | Fri 04/04/03 | 0% | |
| 100 | Coding & Testing | 56 wks | Mon 04/07/03 | Fri 05/07/04 | 0% | |
| 101 | FITS/AIPS++ Extensions | 25 wks | Mon 05/10/04 | Fri 10/29/04 | 0% | |
| 102 | System Integration & Testing, Penticton | 43 wks | Tue 12/14/04 | Wed 10/12/05 | 0% | |
| 103 | M&C System Rdy For WIDAR Correl Tst & Dev Support | 0 wks | Thu 12/01/05 | Thu 12/01/05 | 0% | |
| 104 | ||||||
| 105 | M&C System, Ready For Archive | 0 wks | Mon 04/17/06 | Mon 04/17/06 | 0% | |
| 106 | ||||||
| 107 | 6.10.20.35 Detailed Design & Coding | 386.2 wks | Wed 07/17/02 | Mon 01/25/10 | 0% | |
| 108 | Observing Layer | 52 wks | Wed 07/17/02 | Tue 07/22/03 | 0% | |
| 109 | Scan Setup & Supervision | 52 wks | Wed 01/22/03 | Tue 01/27/04 | 0% | |
| 110 | Antenna Control | 55 wks | Wed 07/17/02 | Tue 08/12/03 | 0% | |
| 111 | Full Support, Enhanced Antennas | 0 wks | Thu 04/08/04 | Thu 04/08/04 | 0% | |
| 112 | Monitor Data | 18 wks | Wed 07/17/02 | Tue 11/19/02 | 0% | |
| 113 | Warnings & Alarms | 26 wks | Wed 11/20/02 | Tue 05/27/03 | 0% | |
| 114 | Data Flagging | 26 wks | Wed 05/28/03 | Thu 11/27/03 | 0% | |
| 115 | Logging | 26 wks | Fri 11/28/03 | Tue 06/01/04 | 0% | |
| 116 | User Interfaces | 104 wks | Wed 07/17/02 | Tue 07/27/04 | 0% | |
| 117 | Hybrid Array support | 52 wks | Wed 07/17/02 | Tue 07/22/03 | 0% | |
| 118 | Correlator, at VLA Site | 152 wks | Mon 07/03/06 | Mon 06/15/09 | 0% | |
| 119 | Begin Installation of Correlator at VLA | 0 wks | Mon 07/03/06 | Mon 07/03/06 | 0% | |
| 120 | System Integration & Testing, VLA | 48 wks | Mon 07/31/06 | Wed 07/04/07 | 0% | |
| 121 | Preparation for Correl Observations | 23.5 wks | Thu 01/18/07 | Mon 07/02/07 | 0% | |
| 122 | Begin Correlator Test Observations | 0 wks | Wed 07/04/07 | Wed 07/04/07 | 0% | |
| 123 | Coding of Operational Sftwre, Correlator | 100 wks | Thu 07/05/07 | Mon 06/15/09 | 0% | |
| 124 | EVLA Correlator Operational | 0 wks | Mon 06/15/09 | Mon 06/15/09 | 0% | |
| 125 | VLA Correlator Shutdown | 0 wks | Mon 01/25/10 | Mon 01/25/10 | 0% | |
| 126 | Data Archive Interface | 39 wks | Tue 01/20/09 | Mon 10/19/09 | 0% | |
| 127 | Image Pipeline Interface | 39 wks | Tue 01/20/09 | Mon 10/19/09 | 0% | |
| 128 | ||||||
| 129 | Last Antenna Converted to EVLA Design | 0 wks | Mon 03/03/08 | Mon 03/03/08 | 0% | |
| 130 | ||||||
| 131 | Last New Receiver Installed | 0 wks | Mon 05/03/10 | Mon 05/03/10 | 0% | |
| 132 | ||||||
| 133 | EVLA Operational | 0 wks | Mon 05/03/10 | Mon 05/03/10 | 0% |
| ID | Name | Group | Max Units | Peak Units |
|---|---|---|---|---|
| 1 | 100% | 0% | ||
| 2 | 100% | 0% | ||
| 3 | 100% | 0% | ||
| 4 | 100% | 0% | ||
| 5 | 100% | 0% | ||
| 6 | 100% | 0% | ||
| 7 | 100% | 0% | ||
| 8 | 100% | 0% | ||
| 9 | 100% | 0% | ||
| 10 | 100% | 0% | ||
| 11 | 100% | 0% | ||
| 12 | 100% | 0% | ||
| 13 | 100% | 0% | ||
| 14 | 100% | 0% | ||
| 15 | 100% | 0% | ||
| 16 | 100% | 0% | ||
| 17 | 100% | 0% | ||
| 18 | 100% | 0% | ||
| 19 | 100% | 0% | ||
| 20 | 100% | 0% |
| Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
|---|