08/09/2001 EVLA M&C System Software, Milestones Material taken from the NSF Addendum and from the draft transition plan of 07/27/2001. 05/01/2001 Official start of project 02/01/2002 M&C Software PDR (Preliminary Design Review) (project start + 39 weeks) 08/2002 Begin installation of fiber optic cable. No Antennas connected. 01/02/2003 Test & Development Support for Enhanced Antennas Ready (project start + 86 weeks) 04/2003 Testing of 1st Enhanced Antenna (EVLA Antenna) to begin. The testbed will be an antenna, pad, and computer hookup with a full network connection. 01/02/2003 M&C Software CDR (Critical Design Review) (project start + 86 weeks) 07/2003 Begin interferometry tests using an EVLA Antenna and a VLA antenna 10/2003 Freeze Electronics Design Work. Begin Production. 03/2004 Start Installation of new IF/LO/FO system on antennas at the rate of 7 antennas/yr. Full M&C capabilities available. 04/08/2004 Full Support for EVLA Antennas (project start + 151 weeks) Note. Currently there is a mismatch between the 03/2004 date for full M&C capabilities and the date of 04/08/2004 for full support of EVLA antennas. 12/01/2005 Ready for WIDAR Correlator at Test & Development Level (project start + 238 weeks) A large portion of the software development will take place in Penticton. 07/2006 Begin installation of WIDAR correlator at the VLA site. 04/17/2006 M&C System Ready For Archive (project start + 255 weeks) 07/2007 Start test observations with new correlator using EVLA antennas. Twenty two (22) EVLA antennas available. 01/2008 New correlator operational. Old correlator shutdown. 03/2008 Last VLA antenna converted to EVLA antenna. 05/2010 Last new receiver installed.