Updates and Changes

to the EVLA Project Book

Under Revision Control 2002/03/01

 

---

 

The EVLA Project Book is under revision control for:

 

1)      Changes in performance or,

2)      cost changes are > $50K or,

3)      schedule changes are  >2 months.

 

Submit requested changes to Control Board Secretary.

 

 

Members of the Control Board are:

EVLA

Project Manager

Project Scientist

Correlator Project Manager

Sys Engineer Electronics

Sys Engineer Software

*  Secretary, Gene Cole

 

 

 

 

---

 