Rehearsal
NSF EVLA Mid-Project Review
Project Overview Science Drivers, Technical
Requirements (Perley) Baseline Project Definition (McKinnon) Technical, cost,
schedule Metrics for successful
completion Plan for proving
metrics are met. Changes to Baseline
Definition Problems encountered,
resolution |
|
|
NRAO Advisory Panel Reports (McKinnon) Review of Panel membership,
responsibilities, meetings Reports so far NRAO responses |
|
|
Budget, Schedule, Contingency Project Schedule (McKinnon) Completed milestones Remaining milestones Critical path tasks Budget, Contingencies, and
Risks (McKinnon) Contingency Risk Assessment and Mitigation Cost to Complete Descope
Options |
|
|
Descope Options (Perley) Hardware options Software options Delay options Science Impact of Descope Options |
|
|
EVLA Project WBS Tasks: Status of each
against budget and schedule Project Management and
EPO (McKinnon) System Integration,
Civil Construction, Antennas ( FE, LO, FO, IF Systems (Durand) Correlator
(Dewdney)
Progress Overview
Budget and Timescale
Plans for prototype correlator implementation,
checkout, tests
Plans for interim correlator, buildup to
final correlator
Mode testing, performance testing
Programming, staffing, implementation |
|
|
Software, Data Acquisition and Processing
(includes WBS status) Overview ( Monitor & Control
(Sahr)
Data Flow
Components Data
Management & Computing (van Moorsel) Post Processing ( |
|
|
Antenna Performance (Perley) |
|
|
Transition Plan and
Operations Transition Plan (Owen)
Meeting metrics for the successful completion of the
project Implementation
of EVLA antennas in VLA observing
Expected/Required scientific capabilities vs. time
Antenna acceptance requirements EVLA Operations Plan
(Ulvestad) |
|
|